Calculate the prime cost from the following information: Direct material purchased: Rs. 1,00,000 Direct material consumed: Rs. 90,000 Direct labour: Rs. 60,000 Direct expenses: Rs. 20,000 Manufacturing overheads: Rs. 30,000
Not Required
355 MCQ for effective preparation of the test of Cost and Management Accounting of Accounting section.
Read the MCQ statement: Calculate the prime cost from the following information: Direct material purchased: Rs. 1,00,000 Direct material consumed: Rs. 90,000 Direct labo .... ds: Rs. 30,000 , keenly and apply the method you have learn through the video lessons for Cost and Management Accounting to give the answer. Record your answer and check its correct answer and video explanation for MCQ No. 228-230.